During this construction there were a number of interfaces, requiring the machines to transit through new, partially built stations. At one of these stations, new Bond Street, the passage of the eastbound machine was problematic; two high strength concrete diaphragm walls had the potential to halt progress 20m below the surface. With the interface imposing a serious risk of delay to the contract, the project team needed to provide a solution permitting the safe passage of the machine and quickly. This paper describes the solution and how the challenge faced was overcome.

Imagine yourself at London Underground’s Canary Wharf Station. After an afternoon of meetings you set off to catch your next business flight out of Heathrow. Your journey starts by boarding the next available westbound Jubilee Line service. Having interchanged, 66 minutes later you arrive at Heathrow Central, ruffled by the heat and overcrowding experienced during your journey.

When Crossrail opens in 2018, this journey will be very different. By jumping on the next available, spacious westbound service, you will be propelled across central London and on to Heathrow Central comfortably, efficiently, and without the need to change. Plus, the journey will take no longer than 39 minutes.

When complete, the rail link promises to provide many more improved journeys, a needed boost to the economy and a 10 per cent increase to London’s existing rail capacity.

The project, which was conceived in the late eighties, connects Maidenhead and Heathrow in the west to Shenfield and Abbey Wood in the east through the use of 90km of above ground (National Rail) lines and 41km of newly constructed tunnel.

Contract C300 – Western Tunnels comprised the construction of 6.8km of twin – bore 6.2m I.D segmental lined tunnel from Royal Oak portal to Farringdon Station.

The contract was awarded in 2010 to a joint venture consisting of BAM Nuttall, Ferrovial Agroman and Kier Construction (BFK). The construction of the Western Tunnels started in 2012 and completion of the second drive was reached in January 2014.

Figure 1, below shows the alignment of the Western Tunnels stretching across central London. The geology encountered along the first 5,000m of the drive was predominantly the upper and lower units of the London Clay. In the east and final 1800m, the alignment declines through the units of the Lambeth Group towards Farringdon Station, where at any time, clay, sand, gravel and laminated layers were simultaneously present at the face.

Such ground conditions led to the design of two soft ground TBMs, which in this instance were manufactured by Herrenknecht. The 7.1m diameter EPB shields had a spoke type cutting wheel with a 55 per cent opening ratio. The cutting wheel tooling comprised a combination of tungsten carbide cutting knives, rippers and cutting discs on the outer radii. In the centre a nosecone was fitted to promote the flow of clay into the excavation chamber.

At different points along the drives the TBMs were required to interface with new, partly constructed, Crossrail stations. These interfaces proved to provide the biggest construction challenges as they required the TBMs to mine sub-surface elements, whether they were piles, diaphragm walls, or zones of foam concrete used to backfill previously excavated sprayed concrete lining (SCL) works.

This paper will focus on the interface of the eastbound machine at the new Bond Street Station and the challenge that it presented.

Bond Street Interface
Situated in the heart of Mayfair is the new Bond Street Station. Here Crossrail is connected to existing London Underground (LU) Central and Jubilee Lines via a series of ticket halls, passages and station platforms.

Advance civils at the station began in August 2011 through contract C411 (table 1), which involved the construction of two station box structures, namely the Eastern and Western Ticket Halls .

As the eastbound TBM advanced through the station, it was required to break into, transit across and break out of both ticket hall boxes.

The Western Ticket Hall comprises a 1.2m thick diaphragm wall (D-wall) of top down construction. Here the TBM break in and break out points were 12m (8 rings) apart and at a depth of 20m below the ground surface in the London Clay (Figure 2).

In the area surrounding the ticket hall a number of critical assets are present, most notably the north and southbound Jubilee Lines which lay 4m below the invert of the eastbound tunnel extrados. Their close proximity placed them within the zone of influence of the TBM during its transit through the ticket hall. Above ground an abundance of commercial and residential units can be found, some of which were identified as potentially sensitive to the ground borne noise and vibration (GBNV) associated with construction works. One of these receptors, Grays Antiques, was considered high risk due to the fragile and high value nature of its stock.

Initial plans had set out for the free air transit of the TBM across the previously excavated ticket hall, but due to variation in the station excavation programme, the box would now remain largely unexcavated on the arrival of the machine.

At the break in and break out points, the ticket hall D-walls comprised GRP reinforcement cast into structural concrete of an estimated strength of 65N/mm. Given the machine had been optimised for soft ground performance, such wall properties gave rise to a problem. The strength and thickness of the walls introduced a significant possibility of wear to the cutting tools and the protruding nose cone during excavation.

The Herrenknecht cutting wheel had the ability to employ two-ring discs (for harder material) on a number of radii, but with the nearest disc track 1.1m away from the centre, even with these tools, the potential for wear to the nosecone remained.

Wear to the nosecone cutting tools during the breakthrough was seen as a significant issue, as repair or replacement of the tools from within the walls would be difficult, time consuming and costly to achieve.

Given the risk of attempting the breakthroughs with ‘do nothing’ approach the project team set out to find a solution that would provide the quick and safe passage of the machine through the ticket hall, whilst minimising disruption to the surrounding area.

Consideration of options
During a series of meetings between the parties involved, two initial solutions came to light. The first solution was proposed by TBM manufacturer Herrenknecht and aimed to increase the concrete excavation performance of the central area of the cutting wheel through a number of modifications (Figure 3, above). The second solution took a different approach. By excavating a small area of the northeast corner of the ticket hall, in advance of the main station programme, areas of the D-walls could be broken out from inside.

An assessment of the two solutions was undertaken in which a number of drawbacks were identified. Even with the cutting wheel modifications further time consuming tool changes were likely to be required whilst mining through the high strength concrete walls. The proposed ticket hall excavation and breakout works would be carried out using contract C300 resources working from the contract C411 site. Such a set up would give rise to a complex work environment and contractual issues which would be hard to overcome. Furthermore, initial estimates suggested the works could delay the TBM by 9 to 11 weeks.

In a set of follow up meetings the team discussed a less conventional approach to the problem, which involved the construction of a staged heading in front of each D-wall. These headings would be driven from the TBM excavation chamber, by hand, using traditional timbering techniques. On completion of each heading, sections of the D-wall which lie directly in front of the nose cone would be demolished from within the timber / steel lined cavern.

The proposal had a number of advantages over the previous solutions. Gaining access to the walls in such a way eliminated the complexities of C411 site working, whilst given the confined nature of the breakout works, the impact of ground borne noise and vibration would be significantly reduced. With an estimated programme of two weeks per wall, implementation of the solution would also be significantly shorter than the alternatives.

Although historically, surface settlements related to traditional timbering works have caused little issue, the potential impact of the solution was first considered. By assuming a worst-case volume loss of three per cent during construction, the team assessed the potential settlement impact to assets above the excavations. It was concluded that even with a volume loss of this magnitude there would be little or no impact on the piled foundations of the surrounding buildings. Furthermore, services in the area identified as susceptible to damage from settlements had been previously replaced with flexible, plastic alternatives.

The construction of the headings was seen as a challenge, but with an abundance of handwork-experienced miners already employed on the project, the team was confident the work could be executed safely and accurately. This combined with the advantages already identified saw the third solution selected

The chosen solution

  • Advance the TBM towards the ticket hall; park a short distance from the first wall.
  • Gain access to the excavation chamber using the air locks.
  • Construct the staged timber heading in front of the cutting wheel, exposing the area of D-wall with which the nosecone will intersect.
  • Breakout a 2.1m diameter circular section of the wall positioned directly in front of the nosecone.
  • Change the existing clay ripper tools for two-ring discs to provide additional breaking power to other areas of the cutting wheel.
  • Advance the TBM through the heading and break through the wall, building rings behind the shield normally
  • Back-grout the rings built within the heading, filling any remaining void left from the heading excavation.
  • Repeat process for the second D-wall.

Design of Timber headings

Key requirements
Having selected the preferred solution, the task of the team was to develop an effective timber heading design, which permitted simple and safe construction.

The first fundamental design requirement was for each heading to remain in position during the advance of the TBM through the D-walls. To achieve this, the crownbars (a horizontal component which carries the load of the timbers), had to be supported such that the cutting wheel could rotate, unhindered, whilst allowing for the advance of the shield through the excavation. Given the implications of a collapse during this advance, the stability of the structure was of upmost importance.

In order to carry out the required breakout works, the headings had to expose the D-walls to a level below the axis of the TBM cutting wheel. Furthermore, the depth of each heading had to be sufficient to accommodate the required tooling for the job and provide ample space to carry out the works safely.

Given that the TBM excavation chamber air locks were going to provide the sole access to the work area, the materials used had to be of a suitable size and weight for ease of handling. Structural elements such as the crownbars needed to be designed in such a way to permit their erection in a confined space in front of the TBM.

The solution resulted in the first heading remaining permanently in the ground outside the ticket hall, therefore the materials used had to resist rotting. With the second heading this feature was less important; future excavation of the ticket hall would unearth the structure.

Due to the limited ventilation possibilities to the work area, the construction method had to limit, if not eliminate the need for welding. Nevertheless, the materials used for the works required a good level of fire resistance.

Design
When excavating a tunnel in London Clay, theoretically the following things happen. Firstly the initial excavation results in a loosened zone around the subsequent void accompanied by an arching of the ground prior to the installation of excavation support.

Secondly, the load experienced on those supports gradually increases due to the long-term plastic behaviour of the soil, squeezing the excavation. Taking this, and given that the design life of each heading would be no longer than two weeks, a temporary approach could be taken to the design loading in which only a percentage of the soil column above the excavation was mobilised.

There are a number of methods that permit the calculation of the short term ground loading just described, but here designer Alan Auld Engineering, selected Protodyakonov’s de-coupled arch theory. The theory assumes a loosened zone around an opening independent of depth (Figure 4, opposite). This loosened zone of parabolic nature is a function of parabola width and soil strength factor (London Clay = 1).

In this instance the time dependant loading set out in LU guidance (LU G055 – Civil Engineering – Deep Tubes and Shafts) was not considered due to the small size of the opening, the frictional support provided by the D-wall, and the containment of the TBM cutterhead. LU guidance does not specifically take into account tunnel size and is based on empirical data observed from LU tunnels of a range of sizes. Generally in smaller openings a greater degree of soil arching can take place over an excavation resulting in a reduction of stress on the tunnel crown.

In addition to the loading provided through Protodyakonov’s theory, the side legs, which would provide a temporary vertical support during each heading stage, were checked for adequacy against wedge failure. Such failures, in the London Clay, are traditionally known as ‘greasybacks’ and arise from naturally occurring discontinuities in the soil.

The heading elements were designed to ultimate limit state using a combination of BS EN 1990:2002 (Basis of structural design), BS EN 1995 1 – 1 – 2004 (Design of timber structures) and BS EN 1993- 1-1:2005 (Design of steel structures). TEDDS, a structural design software, was employed to check the adequacy of steel members.

A cross section through the resultant design can be seen in Figure 5. The final design included a traditional timber structure using 200mm by 100mm Grade C24 tanalised timber throughout and 14no UC 203 x 203 x 46 crownbars spanning from the shield to the D-wall at 1m centres. The crownbars were supported at the D-wall with anchored brackets, and on the TBM shield 1.2m outbye of the cutting wheel edge with hardwood blocks fixed by a welded skid support. The skids role was to permit the sliding of the supports over the shield on the advance of the TBM. The length of the skid was sized in a way to eliminate the possibility of the support jamming or becoming stuck in the shield articulation joints. The end of each crownbar was pocketed into the clay, this effectively restricted vertical and lateral movement during the advance of the TBM. In front of the cutting wheel each heading provided a minimum 1.5m working space between the nosecone and D-wall, ample space for the stitch drill / hydraulic bursting breakout method that had been selected for the demolition.

The crownbars were inclined at six degrees from the horizontal, this resulted in a much discussed 450mm clearance between the outer radius of the cutting wheel and the underside of the wall anchored bracket. The 450mm was a trade-off between the minimum safe distance to allow the cutting wheel to rotate and the time required to carry out each excavation.

The crownbars included a central splice detail that permitted the handling of smaller elements through the air locks. Bracing between crownbars provided rigidity, an essential aspect during the movement of the shield.

The heading invert was battered in a channel like fashion, this promoted the drainage of water arising from the coring works into the excavation chamber. Here submersible pumps would transfer any water to the TBM waste water system and out of the tunnel (Figure 6).

Safeguarding the china
Given the key receptors surrounding the ticket hall, the potential GBNV impacts arising from the works were first assessed in order to justify a need for monitoring.

Experience gained through on-going BFK SCL works in the area (C410 Bond Street Station platforms) led to a belief that there would be no ground borne noise disruption at two key residential receptors, The Cavendish Building and Hanover Flats. However, Gray’s Antiques, a two floor building, which houses 200 antiques dealers selling items ranging from irreplaceable ancient artefacts to modern day collectables, raised concern.

Assessment of the building’s interior led to the setting of a vibration threshold level of 3mm/s for the duration of the works.

Trained acousticians equipped with a series of ultra-quiet, ultra-low frequency accelerometers were tasked with monitoring vibration levels, halting the works in the event of a breach.

Construction

Approaching the ticket hall
Construction began with the advance of the TBM towards the ticket hall. To validate the position of the first wall, the face was probed from within the excavation chamber. Validating the wall position was an essential aspect of the approach, as parking too close would reduce the workspace in front of the cutting wheel, hindering the construction of the timber heading and the breakout works to follow.

Transforming the excavation chamber
Having reached the required position the excavation chamber was depressurised and the level of spoil within the chamber reduced. The remaining spoil provided an element of earth balance below axis, whilst above axis the face was boxed up with timber between the cutting wheel spokes. These timbers would keep the face under control prior to the development of the heading.

Following this, the excavation chamber was transformed to accommodate the upcoming handwork. Secondary ventilation, lighting and power made its way to the excavation chamber through the bulkheads redundant smalleropenings. Aseriesofmicro conveyors passing through the material lock and discharging onto the TBM conveyor system would aid the removal of spoil from the work area. The man lock at the top of the excavation chamber was kept free for the passage of miners, primary ventilation, tools and materials. The first TBM gantry also had a new purpose, here a backup team of miners worked to prepare the timber, grout and steel required for the works.

Traditional timbering
Equipped with FL22 clay spades the miners began the timbering works by driving an initial box heading towards the D-wall through the window of two cutting wheel spokes orientated to the vertical. Once complete the unearthing of a smooth D-wall finish was a welcome sight, this would aid the installation of the crownbar wall supports.

Advancing back over the shield, the first crownbar pockets were excavated. The excavation of the pockets was particularly difficult due to the required depth and narrowness of the opening.

In hindsight the crownbars should have been set slightly higher at the shield to aid the excavation and installation of the welded skid supports. Nevertheless, the installation was still achievable and the level of vertical and lateral restraint provided by the pockets was excellent. Following the completion of the pockets the first crownbars were erected with the aid of a temporary support system.

Over the next six days, the seven stages of the heading works were carried out, in which 90t of London Clay was removed from the excavation (Figure 7).

Throughout this period the timbering was regularly inspected to ensure proper tightening against the face. Tightening, which is also known as pre-loading, is a fundamental aspect of timbering within London Clay. In short term excavations such as this, failure arising from overburden pressure is a rarity, but is more likely to result from the local wedge failures previously described. Tightening timbers against the clay effectively restrains any potential soil wedge by restricting movement. Here, the tightening of headboards (a horizontal timber which spans between crownbars) was achieved with the use of hard wood wedges and grouting of the void between timber and the clay face on regular intervals. The latter also ensured full transfer of load to the timber-steel support system, whilst sealing the face to prevent drying and deterioration of the soil.

Management of percussive tools
Since the introduction of legislation controlling vibration at work, the management of exposure to hand arm vibration (HAV) has become a major aspect of traditional timbering works due to the nature of the percussive tools used. Exposure limits set out in these regulations are fundamental to this management and in certain circumstances can make such work costly and hard to achieve.

Here central to the management of HAV was the correct selection of gang size and baseline scoring of the men. The timbering works were carried out around the clock, with three shifts per 24 hour period.

Each shift comprised a gang of 16 miners working 8 hours at the face. Of the 16 miners, 10 were on rotation for the handwork, the remaining six provided backup from the TBM.

Using best practice guidance (BTS – The Management of Hand-Arm Vibration in Tunnelling) estimated trigger intermittency levels for excavation in London Clay were consulted and used as the basis of rotation management. These values were later confirmed through monitoring carried out during the works.

Breakout of the D-wall
On the completion of the first heading the breakout works commenced. The circumference of the breakout section was stitch-cored to provide a relief line to break to.

A relief line allows the concrete to be displaced when put under tensile stress, which ultimately leads to its failure. Additional smaller diameter cores were drilled in the centre of the concrete mass to accommodate a low vibration hydraulic wedge, which was used to burst the concrete.

The breakout works went very well, taking just two days to complete.

Breakthrough
Following the breakout, the TBM advanced through the heading and began mining the first wall. During this 1.2m advance through the concrete a penetration rate of 5mm/ rotation was maintained to keep torque and heat to a minimum. The breakthrough was a success taking just three hours to complete.

Following the success of the first D-wall the TBM advanced to opposite side of the ticket hall where the process was repeated.

From start to finish the ticket hall transit took three weeks to complete, this was a significant gain on the initial programme. During the works the installation of a tunnel conveyor booster motor was re-programmed to minimise lost time.

The acousticians positioned at Gray’s Antiques obtained satisfactory results. The work produced vibration peaks well below pre-determined trigger levels and more importantly no stock at Gray’s Antiques was damaged.

The Jubilee Lines experienced 1mm heave as a result of the TBM transit and above ground recorded surface settlements were negligible.

Following the breakthrough of the second wall the TBM was stopped again for a cutting wheel inspection. There was no wear to the clay knives and hard facing. More crucially, no damage to the nose cone and the surrounding area was sustained.

Conclusion
The new Bond Street interface had the potential to inflict serious cost and delays to the Western Tunnels project. Through a thorough assessment of the options available the team were able to identify a solution that eliminated the risk of damage to the TBM tooling, whilst minimising disruption to the adjacent station works and surrounding area.

The solution was successful in achieving its objectives and the eastbound TBM went on to finish the remainder of its drive in a successful manner. Interfacing a TBM with a station may seem simple on paper, but in reality it can produce some of the more complex challenges faced on modern day metro projects. The obstacles the new Bond Street Station presented reinforces the need for good detail at these interfaces and an understanding of requirements between all parties involved.

The way in which the project team overcame this challenge reinforces the fact that techniques used to construct the first tube lines 150 years ago are still an invaluable asset to the industry today