The Daniela Tunnel, through Momaia Hill, is 1,350m long.

Crews have completed 665m (50%) of the floor slab and 615m (46%) of the upper vault of the Daniela Tunnel.

The company is also making progress on the parallel Alina Tunnel, with 80% of excavation completed and 610m of the base plate built.

If the current pace of construction is maintained, excavation of the Alina Tunnel will be completed in April.